projects archive
- Surface Water Treatment Improvements -2006
-
This project included miscellaneous plant modifications including the installation of a WEDECO UV disinfection system.
- Community water wells #1, 2, 3 and 4- 2006
- Summit Controls provided electrical construction and SCADA design services for Empire Residential Land Developer for 4 new water wells
- Town of Clarkdale Wastewater Treatment Plant Improvement Project- 2007
- Project management, control panel design, and electrical contracting services were provided to increase treatment plant capacity.
company projects
0.65 MGD Wastewater Treatment Plant Expansion
The Camp Verde 0.65 MGD Wastewater Treatment Plant Expansion consists of replacing an existing 0.28 MGD aerated lagoon wastewater treatment plant with a new 0.65 MGD extended aeration system capable of achieving nitrification/de nitrification and aerobic digestion of sludge. The new facility will be capable of producing Class B+ reclaimed water in accordance with the Arizona Administrative Code. Appurtenant facilities shall include a new headworks, a septage receiving facility, ultraviolet disinfection equipment, a sludge dewatering system and all necessary site work, piping, valves, pumping equipment and electrical and instrumentation systems required for a complete and operable system. .
Pressure Zone Booster Station
Iron Springs Road Booster Station Project consisted of constructing a new pump house and extension of a water main. Summit Controls designed, installed and commissioned the electrical and controls system for the facility.
projects gallery